iMANAGE was part of a team of experts and professionals entrusted with the project management of the erection of protective shelters on the Hagar Qim and Mnajdra temples. iMAN’s role was that of site supervision, project and contract management as well as the co-ordination of inputs from the various consultants within the team that were critical for the successful delivery of this complex and extremely sensitive project on behalf of the Client.  

The works consisted of the construction of anchorage piles as well as the manufacturing and erection of structural arched trusses and installation of the protective fabric along with architectural lighting, security systems and installation of interpretation boards.

Client: Heritage Malta

Project budget was €5m (part-financed by the EU)

Completed in 2010